The oil production wells and a water source well at Situche Central field will require artificial lift as planned with the subsurface basis of design. Artificial lift for the oil producers is required to maximize ultimate recovery and maintain oil production with increasing water cut. The main goal for Situche Artificial Lift is to provide a lift system that is efficient, the least complicated and robust enough to survive Situche downhole conditions for a minimum 2 ½ years. Such a lift system would be safer (less rig time for pump repairs and less equipment handling and transport) and have the least impact on the environment. Situche Central is a seven well development expected to be sanctioned in Q1 2013, with first oil in 2015. The successful development of Situche Central requires the re-completion of the two existing exploration wells and the drilling of two additional oil producers and water handling wells. This is the Phase 1 development.